Rezolv Energy has signed a grid connection agreement for the Dunarea East & West wind parks, a 600 MW project in Constanța county. The project is being developed by Rezolv in partnership with Low Carbon.

Dunarea East&West will share the same grid connection point, which will require the construction of a new 400kV interconnection substation to feed the power produced into the transmission network.

Work will commence in line with the Dunarea project timeline, with a view to the power coming onstream from 2026.

Dunarea East&West will be designed, constructed and operated to the highest environmental, social and governance (ESG) standards.

The clean power produced will be sold to commercial and industrial users through long-term power purchase agreements.

Rezolv, which launched 18 months ago, already has over 2GW of clean energy projects being prepared for construction in South Eastern Europe.

Supported byElevatePR Tech

RELATED ARTICLES

Supported byCarbon Trading Exchange
Supported byInvitation for Europe
Supported byClarion Energy
Supported byVirtu Energy CBAM Electricity