Businesses in Republika Srpska are expected to see higher electricity prices starting January 2027, with households scheduled for adjustments from March. The size of the increases has not been announced. Existing residential prices are set to remain in place until March, while the government considers measures to limit the impact of later changes on households.
Residential tariffs and steps to protect consumers
Authorities said residential pricing would be maintained until March as policy options are reviewed for the period after that date. ERS management defended the approach, with Luka Petrović describing household tariffs as among Europe’s lowest. Petrović linked the tariff level to the government’s commitment to protecting consumers from high energy bills.
Officials indicated that higher tariffs could improve the sector’s finances next year. The immediate focus remains on supply security for winter generation rather than on the longer-term pricing schedule. The winter challenge is tied to coal availability and restoring dependable output at a key thermal facility.
Ugljevik thermal plant disruptions drive urgent fuel actions
The authorities’ more immediate priority is restoring reliable production at the Ugljevik thermal power plant. Disruptions at the facility have led to efforts focused on fuel supplies and measures intended to prevent electricity restrictions. Luka Petrović, general director of state-owned utility ERS, said the company would arrange urgent coal purchases to restart generation and keep the plant operating.
Alongside short-term procurement, authorities are addressing longer-run constraints related to coal extraction. Access to the Ugljevik East 2 mining area is described as dependent on resolving property rights issues. Unresolved inheritance disputes have delayed land expropriation and limited access to areas needed for coal extraction.
Legislation planned for mine access and strategic energy projects
The government is preparing legislation aimed at removing administrative obstacles affecting the mine. A broader law covering strategic infrastructure is also expected before the end of 2026, with the stated aim of accelerating major energy projects. These steps are intended to support access needed for coal production linked to winter supply requirements.
Energy Minister Petar Đokić ruled out privatisation as a response to sector difficulties. He said ERS would remain publicly owned and operate under stronger state oversight. ERS management has continued to defend its residential pricing policy while authorities work on both fuel supply and mine-related access issues.