Slovenia is set to enhance its renewable energy landscape with the development of a new solar power facility in Maribor, utilizing a former landfill site. The project, spearheaded by Dravske Elektrarne Maribor (DEM), has secured a co-financing agreement with the government, marking a significant step towards sustainable energy production in the region.
The solar installation, designated as ZOOP, will be located on the site of the closed Pobrezje landfill. Once operational, it is projected to generate approximately 12 GWh of electricity annually, contributing directly to the national electricity network. This initiative aligns with Slovenia’s broader goals of increasing renewable energy capacity and reducing reliance on fossil fuels.
With an estimated total investment of around 9.6 million euros, funding for the project will derive from multiple sources, including nearly 4 million euros from Slovenia’s Modernization Fund. The remaining funds will be provided by DEM. Construction is slated to commence in the first half of 2026, following the selection of contractors, with expectations for the facility to become operational by the end of 2027.
This project represents one of the initial applications of newly enacted legislation that facilitates the establishment of renewable energy facilities on decommissioned landfill sites. Environment, Climate and Energy Minister Bojan Kumer has indicated that there are currently 63 locations across Slovenia that could potentially host similar renewable energy developments.
DEM plays a crucial role in Slovenia’s energy sector, operating eight large hydropower plants along the Drava River, alongside five smaller hydropower facilities and four existing solar power plants. Collectively, these assets contribute to nearly a quarter of Slovenia’s total electricity generation, underscoring DEM’s strategic importance in advancing the country’s energy transition.