Montenegro: CGES launches €36 million modernization of Brezna substation with EBRD and EU support

Supported byClarion Energy

Montenegrin electricity transmission system operator CGES has initiated a procurement process for two 400/110 kV, 300 MVA power transformers, marking the beginning of a 36 million euro modernization project for the Brezna substation in northwestern Montenegro.

The upgrade will convert the current 110/35 kV installation into a three-voltage 400/110/35 kV facility, which will be connected through the upcoming 400 kV Lastva–Pljevlja transmission line. Financing for the project includes a 28 million euro loan approved by the European Bank for Reconstruction and Development (EBRD) in July 2024, alongside Montenegro’s application for an additional 7 million euros in grants from the European Union’s Western Balkans Investment Framework (WBIF).

Supported byElevatePR Tech

RELATED ARTICLES

Supported byCarbon Trading Exchange
Supported byInvitation for Europe
Supported byClarion Energy
Supported by