HomeElectricityBosnia and Herzegovina's EPBiH Initiates €32 Million Project to Reduce Emissions at...

Bosnia and Herzegovina’s EPBiH Initiates €32 Million Project to Reduce Emissions at Kakanj Power Plant

Supported byClarion Energy

Investment in Environmental Compliance

This month, Bosnia and Herzegovina’s state-owned utility, EPBiH, has launched a significant procurement initiative for the construction of a flue gas denitrification facility at the Kakanj thermal power plant. The investment, valued at approximately €32 million, aims to align the country’s coal-based electricity generation with stringent European environmental standards.

Tender Process and Technological Upgrades

The tender process is structured as a multi-stage procedure, beginning with prequalification followed by initial bids, negotiations, and final offers. The project will implement selective catalytic reduction (SCR) technology on units 6 and 7, significantly reducing nitrogen oxide (NOx) emissions.

EPC Turnkey Model Implementation

The project will be executed under an EPC turnkey model, placing full responsibility on the contractor for design, construction, and commissioning. Key tasks include preparing technical documentation, conducting preliminary activities, constructing SCR systems, and performing testing and trial operations. Completion is anticipated within 24 months from the contract’s effective date.

Supported byVirtu Energy

Regulatory Compliance and Emission Reduction Goals

This initiative is part of Bosnia and Herzegovina’s commitments as a member of the Energy Community, particularly concerning compliance with EU directives that limit emissions of SO₂, NOx, and particulate matter from coal-fired power plants. The upgrade aims to meet the stipulations of the National Emission Reduction Plan, targeting NOx emissions to not exceed 150 mg/Nm³.

Long-Term Operational Benefits

The newly installed SCR systems are expected to have an operational lifespan of around 20 years, with project completion projected by the end of 2027. Once operational, units 6 and 7 are expected to generate up to 2 TWh of electricity annually. This modernization effort will not only enhance environmental compliance but also yield significant public health benefits while fostering local company participation during both construction and operation phases.