Slovenia’s government has concluded that the wider public benefits of the long-delayed Mokrice hydropower scheme outweigh its environmental impact, clearing another major regulatory obstacle. The project, led by Hidroelektrarne na spodnji Savi, could move towards construction in 2027 if it secures the remaining approvals and faces no further delays from legal challenges. The plant is expected to produce enough electricity for more than 30,000 households and will be part of wider flood-protection infrastructure in the Lower Sava region.
Environmental requirements
The reservoir could also support regional water management during droughts. Approval is subject to extensive environmental conditions, including habitat restoration, protection for fish and spawning areas, and passages for aquatic organisms. Additional conservation measures will be required in the Natura 2000 protected area, alongside continued environmental monitoring.
Construction still requires permits
The latest decision does not itself authorize construction. The developer must complete the environmental procedures and obtain a valid building permit. Further court challenges remain a risk to the project timetable.