HomeGasRomania Targets 430-MW Iernut Plant Operation by June 2027

Romania Targets 430-MW Iernut Plant Operation by June 2027

Supported byClarion Energy

Romania’s delayed Iernut gas-fired facility could enter commercial operation by the end of June 2027. Synchronization with the national electricity network is targeted for the first quarter. Under the revised schedule, the 430-MW plant would connect to the grid by March, with technical testing and commercial operation to follow before the end of the second quarter.

Remaining work and plant design

State-owned gas producer Romgaz is coordinating the remaining work as general contractor. General Electric remains involved at the site. The combined-cycle plant is designed for projected gross electrical efficiency of 56.4% and flexible generation that can respond to changes in demand and renewable output.

Black-start capability and Romgaz strategy

Iernut will have black-start capability, enabling it to restart without an external electricity source. This could support restoration of Romania’s grid after a major system outage. The project is also part of Romgaz’s strategy to expand beyond natural gas production into electricity generation.

Supported byElevatePR Tech

RELATED ARTICLES

Supported byCarbon Trading Exchange
Supported byCBAM Electricity verification
Supported byClarion Energy
Supported byVirtu Energy CBAM Electricity