Construction of the Mintia gas-fired power plant in western Romania has surpassed 80% completion, with Romanian authorities placing the project at approximately 83% complete. The development is backed by investments exceeding 1.2 billion euros. The project is now in its final development phase ahead of planned commissioning activities.
Planned capacity impact on Romania’s electricity system
When the first phase becomes operational, the facility is expected to add around 1.7 GW of capacity to Romania’s national electricity system. Romanian authorities link the timing to ongoing tight electricity market conditions and elevated power prices. The project is positioned to increase domestic generation and support supply stability.
The project’s role in regional gas supply planning is also tied to the Neptun Deep offshore development, which is scheduled for later this decade. Expected future gas output from Neptun Deep is described as a factor that would support the economic viability of new gas-fired generation in the region.
Site visit and remaining steps before commercial operation
During a recent site visit, interim Prime Minister Ilie Bolojan met with representatives of developer Mass Global Energy Rom. The meeting also included officials from transmission system operators Transgaz and Transelectrica. Discussions focused on remaining milestones needed before the plant can enter commercial operation.
Commissioning timeline for grid synchronization and fuel readiness
A key commissioning step is scheduled for June, when testing of the connection between the power plant and its associated substation is expected to begin. Network integration will then continue in phases through October as the facility is gradually synchronized with Romania’s electricity grid. Authorities have indicated that gas supply infrastructure must be ready by August.
The first electricity generation is currently planned for September 2026. Officials said close coordination among stakeholders is important to avoid delays during testing and commissioning . The government also described the investment as strategically important for strengthening national energy security and diversifying the electricity mix.
Regional development considerations for Hunedoara County
The government further cited support for regional economic development in Hunedoara County. Once fully completed, the TPP Mintia project is expected to become the largest single-site gas-fired power plant in the European Union. The project is therefore framed as a major addition to Europe’s energy infrastructure .