HomeGasRomgaz targets first power from Iernut gas plant before year-end 2026

Romgaz targets first power from Iernut gas plant before year-end 2026

Supported byClarion Energy

Romgaz is aiming to generate the first electricity from its 430 MW Iernut gas-fired power station before the end of 2026, with Romania adding more wind and solar capacity. The project is positioned to provide additional flexible generation for a power system facing higher volumes of variable renewables.

Iernut construction delays and May procurement changes

Construction of the Iernut plant began in 2016, but contractual disputes and repeated implementation problems pushed commissioning well beyond the original schedule. A government memorandum approved in May eased procurement procedures for the remaining works. The change is intended to give Romgaz more flexibility to accelerate completion.

Site activity ramp-up and grid synchronisation timeline

Work at the Iernut site is expected to increase substantially from 1 September. Romgaz believes the plant could be synchronised with the national grid before year-end. The company has not yet confirmed the date for full commercial operation.

Supported byVirtu Energy

Role of flexibility as renewables expand

The value of Iernut for the Romanian market is linked to flexibility as well as headline capacity. The new unit is designed to respond to changes in renewable generation rather than run continuously as conventional baseload. That function is becoming more important as Romanian solar, wind and battery capacity expand and intraday volatility increases.

Generation from existing Iernut units during transition

Until the new plant becomes available, Romgaz continues producing electricity from existing Iernut facilities. This includes a 200 MW coal unit operating at full capacity.