The Hungarian energy landscape is poised for a significant transformation as Green Energy Investor (GEI) embarks on an ambitious project to establish a large-scale wind power complex in the Kisalfold region, specifically near Vadosfa. This initiative aims to enhance the country’s wind capacity by adding 499 MW through the installation of 70 high-capacity turbines, marking a pivotal moment for Hungary’s renewable energy ambitions.
Upon completion, the new wind farm is projected to produce approximately 1,200 GWh of electricity annually. This development comes at a time when Hungary’s total wind capacity has stagnated at around 330 MW over the last decade, particularly as solar energy projects have surged. The GEI project represents one of the most significant onshore wind initiatives in recent years, highlighting a renewed focus on diversifying Hungary’s energy portfolio.
The proposed turbines will each have a capacity ranging from 7 to 7.2 MW and will be strategically placed within a 15-kilometer radius of Vadosfa. With an anticipated operational capacity of about 2,500 hours per year, this facility is expected to achieve nearly double the utilization rate of conventional solar plants in Hungary, underscoring its operational efficiency.
As of now, GEI has reached the building permit stage for this project. A comprehensive year-long environmental monitoring campaign concluded earlier this year, providing essential data that has paved the way for formal permitting processes. Infrastructure development for network connection and transmission is slated to commence in late 2026, with the first turbine installations expected in early 2028. Full operational commissioning is projected for late 2029 or early 2030.
The selected turbines are designed with towers reaching up to 130 meters and an overall height of approximately 220 meters, featuring rotor diameters of 90 meters. This design ensures high efficiency even under moderate wind conditions. Furthermore, GEI has assured that noise and vibration levels will remain compliant with regulatory thresholds, with turbine placements exceeding one kilometer from residential and recreational areas—well above the minimum legal requirement of 700 meters.