HomeNews Serbia EnergyTENT power plants stable production results in 2012, 55% of Serbian electricity...

TENT power plants stable production results in 2012, 55% of Serbian electricity comes from TENT TPPs

Supported byClarion Energy

In December 2012, The Company “Thermal Power Plants Nikola Tesla” produced and delivered to the electric power system of Serbia 2,039,863,000 kWh of electricity, that is 1.33% more than planned. Together with non-produced electricity because of the hot and cold reserve that amounts to 34,876,000 kWh, the production plan would be achieved with 103.07%. During this month a total of 13 downtimes were recorded, out of which 10 occurred in TPP NT, two in TPP “Kolubara” and one in TPP “Morava”.

TPP A produced and delivered to electric power system 1,029,421,000 kWh of electricity or 1.21% less than planned. Together with non-produced electricity (16,253,000 kWh) due to the heating reserve, the plan would be accomplished with 105.35%. Power Units А-1, А-3 and А-6 overfulfilled the monthly plan. The first two Units recorded continuous grid operation in December.

Supported byVirtu Energy

In the same period, TPP B produced and delivered to the power system 833,340,000 kWh of the electricity or 5.35% more than planned. Non-produced electricity due to the heating reserve (4,273,000 kWh) would have a minimum impact on the plan increase – 0.60%. This Power Plant did not have any downtimes in December, and the Unit B-2 was operating all the time on the grid.

TPP “Kolubara” produced and delivered to electro energy system 122,970,000 kWh of electricity and achieved plan with 108.82%. Together with the non-produced electricity (7.958.000 kWh) due to heating and cold reserve, the plan would be achieved with 115.87%. Power Unit A-3 had continuous operation on the grid and overfulfilled the monthly production plan,  which was also the case with Unit A-5.

TPP “Morava” produced and delivered to the electric power system 54,132,000 kWh of electricity and achieved the plan with 80.79%. Together with the non-produced electricity (5,942,000 kWh) due to hot and cold reserve, the plan would be realized with 89.66%.
Via railway transport it was delivered 2,783,815 tons of coal to TPP NT A, TPP NT B, and TPPK, which is just 0.36% less than planned. TPP M received both from the underground and open pit mines 58,109 tons of coal, that made 109, 64% of the plan.

Specific consumption of liquid fuels in the Company TPP NT is by 8.37% lower than the standard being 2.15 g/kWh.
The participation of the Company TPP NT in the PE EPS without TPP “Kosovo”, amounts to 58.87% or 79.23%.

In the period January-December of 2012, the Company TPP NT produced and delivered to EPS 19,151,993,000 kWh of electricity by which they achieved the plan with 98.49%. With the electricity being non-produced due to hot and cold reserve, plan would be accomplished with 100.74%.

Source Kwh/Serbia Energy