The sole Montenegrin thermal power plant Pljevlja has been offline since 1 April. It has been successfully reconnected to the network in the evening hours of 24 June.
On 20 April, the Energy Community Secretariat sent an Opening Letter to Montenegro to address its breach of the Large Combustion Plants Directive. In particular, the country’s sole thermal power plant Pljevlja, continues to operate despite the expiry of the limited lifetime derogation period of the plant. Montenegro has to respond until 20 June. Following a written declaration not to operate a plant for more than 20,000 hours after 1 January 2018, the limited lifetime derogation (also known as opt-out) was granted to selected installations by the Energy Community Ministerial Council. It is an implementation alternative to complying with the maximum emission limits set by the Large Combustion Plants Directive. Following the expiry of the 20,000 hours, the plants can only remain in operation if they meet the (stricter) standards of the Industrial Emissions Directive. This is not the case for TPP Pljevlja.