February 12, 2025
Owner's Engineer banner
HomeSEE Energy NewsBosnia and Herzegovina: Extended concession of TPP Ugljevik 3

Bosnia and Herzegovina: Extended concession of TPP Ugljevik 3

Supported byClarion Energy banner

Comsar Energy previously requested for its concession to be extended from 30 to 45 years, now the Government of the Republic of Srpska (RS) once again met the request of Comsar Energy and extended the deadline for the construction and usage of coal-fired thermal power plant Ugljevik 3 to 44 years.

The construction of this power plant has not even started yet, although, according to initial plans, it was supposed to be operational for several years already. The statement from the Government said that the term for which the concession is awarded is extended to 44 years, counting from the day of the contract’s conclusion. The minimum amount of concession fee for the ceded right for the extended duration of the concession is around 1.5 million euros.

In 2018, Russian company asked RS Government to extend the concession granted for the construction of TPP Ugljevik 3 for an additional 15 year or the company will give up the investment. The request includes the extension of the concession period from 30 to 45 years, because the current concession period of 30 years is deemed unprofitable due to lower electricity prices. At the same time, Comsar Energy requested to reduce the power output of the future plant from 600 to 350 MW. However, in early 2020, Comsar Energy requested that the installed capacity should be increased to 700 MW. In March 2011, Government of RS has approved a letter of intent submitted by Comsar Energy Limited regarding construction of second unit in TPP Ugljevik. The investor was selected based on unsolicited bid, without publishing public invitation. TPP Ugljevik 3 will have two 300 MW units and overall cost of the project is estimated at 750 million euros. The joint venture agreement for construction of TPP Ugljevik 3 was signed in July 2011 by the RS Government and Comsar Energy. Comsar Energy is obliged to invest 90 % of the funds, while the coalmine and TPP (RiTE) Ugljevik should invest 10 % of the necessary funds. The government will hold 10 % stake in the joint venture company, by investing the land and existing infrastructure at the site of TPP Ugljevik, while CE will own 90 % stake. TPP Ugljevik 3 would export its entire output to foreign markets and it will not be competitor to local power utility ERS. The construction of the plant has not started yet.

 

 

 

RELATED ARTICLES

Supported byOwner's Engineer
Supported by
Supported byClarion Energy
Supported by
error: Content is protected !!