Thermal power plant Kakanj for six months exceeded the production plan by 11,07%

Supported byClarion Energy

In June, TPP Kakanj exceeded the production plan by 13,66%, while the plan for six-mount production is exceeded by 11,07%. The preview of electricity production by blocks is below:

Planned electricity production of block 5 in June: 51.680 MWh.

Supported byVirtu Energy

Realized electricity production of block 5 in June: 64.108 MWh

The percentage of realization in June:124,05%

The revitalization of 6th block is in progress, so it has not been in operation since 11.03.2011.

Planned electricity production of block 7 in June: 116.280 MWh

Realized electricity production of block 7 in June: